Saturday, July 12, 2008

Days Nine to Eleven

Days 9-11 were mostly detail work and there wasn't a whole lot of change to show on pictures. One day our contractor spent most of the morning looking for the parts to make our heating & a/c ducts come out properly under the new "peninsula." He did a very good job getting this right. Not only does it work nice, it will look good under the peninsula (when the grates are put on after the floor is installed) but he also improved the ductwork in the basement coming out of the funace and up to the kitchen.

The kitchen floor will be installed early next week, then our contractor will put the "kickplates" on at the base of the lower cabinets.

On Day 11 we had the counters measure and a template made for the counter tops. Hopefully they will come in soon as this will be one of the last steps before the sink & appliances can be installed.

Below are some pictures at the end of Day 11. (Only a few handles are missing on our cabinets/drawers...for some close-up shots of the detail work, see Day 12.)